Written answers There are local concerns about increased traffic and blocked access during construction. What specific measures will the developer implement to manage access to the site (specifically the footpath/cycle route connecting Eversley Crescent to West End Road) and to, minimise disruptions to local traffic, and ensure the safety of pedestrians and residents throughout the […]
Archive | Planning
Q1 – Parking – Barn Hotel special meeting questions
Written answer With 72 dwellings and only 26 parking spaces, how does the developer plan to ensure that the development does not contribute to increased on-street parking in the surrounding residential areas? The Planning policy from the London Plan and Hillingdon Local Plan is generally to restrict car parking in line with accessibility to existing […]
Presentation from Barn Hotel’s prospective developers
Presentation by Chad Neaves from Chase New Homes Back to list of questions Back to Introduction To our Q1 – Parking Special Public Meeting – 23 Oct 2024 Introduction & Welcome (3 min 43 sec) Developer’s presentation: overview of plans (11 min 53 sec) Q1 – Parking (2 min 14 sec) Q2a – Access during […]
Special public meeting introduction
The meeting was attended by: Chad Neaves, Development Director of Chase New Homes over 130 residents of Ruislip and Ruislip Manor the Uxbridge & South Ruislip MP Danny Beales (Ruislip Manor’s MP) Ruislip ward councillors Cllr Riley, Cllr Smallwood and Cllr Corthorne Ruislip Manor’s ward councillors did not attend, and instead provided this statement: Special […]
Questions & Answers from our Barn Hotel special public meeting
On Wednesday 23rd October 2024 we were joined at a special public meeting by Chad Neaves from Chase New Homes, the developer that has submitted an application to LB Hillingdon to redevelop the former Barn Hotel in Ruislip We saw a presentation from Chad on the overall propsed plans for the site, and then asked […]